Week #24 — Half the roof is done!

An exciting week here in good old Pererenan. We’ve been fortunate to stay ahead of the rainy season and cover half of the building with a roof. The other half is about two weeks away.

In the meantime we have a crew for building brick walls and then plastering them. When needed the mechanical, electrical and plumbing (MEP) crew come out and set wires into the brick walls:

They also run water pipes through the walls, as well as prepare the drainage system. Offsite, a windows and door crew are working with aluminum and glass.

Tomorrow we meet with a custom furniture maker and will see whether his prices are affordable.


Share

Recent Posts

Best Digital Nomad Accommodations in Bali for Remote Work & Long Stays

Bali has become one of the world’s most popular destinations for remote workers, but choosing…

3 weeks ago

Best Digital Nomad Destinations in Bali: Where to Live, Work, and Thrive

Bali has long been a global magnet for remote workers, but choosing the right base…

2 months ago

Bali Best Day Out From Pererenan: Easy, Beautiful & Unrushed Ways to Explore the Island

Pererenan is more than a peaceful place to stay—it’s one of Bali’s most strategic bases…

2 months ago

Best Areas to Stay Long Term in Bali: A Practical Guide for Couples, Families & Remote Workers

Staying in Bali long term is less about chasing highlights and more about choosing an…

3 months ago

Best Boutique Hotels Near the Beach in Bali: A Curated Guide by Area & Travel Style

Bali’s coastline is dotted with boutique hotels that offer more than just a place to…

3 months ago

Best Places to Celebrate New Year in Bali: From Iconic Parties to Peaceful Coastal Escapes

Bali offers more than one way to welcome the new year. From high-energy beach club…

4 months ago