Category Preliminary Work

Week #15

The structure is now 40% complete. To be clear, that gets you a building with exposed brick walls and openings for doors and windows. Plus, a roof, electric wires and plumbing lines in place. But no “finishes”: construction-speak for bathrooms,…

Week #14

This week we were able to get most of the forms and beams in place to pour the first floor of the residential side of the building. In addition, all of the columns for the first floor of the guest…

Week #13

Not every week is dramatic visually. Sometimes the preparations seemingly slow down construction, but in reality the project still moves along in a timely manner. This week the framing of the first floor (above the basement) of the residential side…

Week #12

Well folks this week we went vertical, including the famed bamboo support posts that temporarily maintain the weight of freshly poured beams and concrete floors until they harden: Does it feel good? Oh yeah, it’s like totally awesome dude :)