Week #07
A LOT of dirt was moved around the property over a period of three days, in preparation for an open basement / parking area. Due to the limited size of the property we decided to be as efficient as possible…
A LOT of dirt was moved around the property over a period of three days, in preparation for an open basement / parking area. Due to the limited size of the property we decided to be as efficient as possible…
An exciting week, as two cement trucks, a pump truck, and a sizable crew poured the four walls for the future swimming pool. In addition, foundation walls and columns went up for the guest side of the living space. A…
This week was at least as productive as the others, although we were in Makassar for several days and didn’t see a bunch of the work that unfolded. Luckily a manager took photos and videos during the time we were…
This week over 75% of the holes were drilled to support the foundation for our future retreat. In addition, steel rebar “cages” were built and placed into the holes in order to increase the strength of the concrete. Unfortunately, the…
Because the building is approximately twelve meters tall (over 39 feet), we had to dig down to really hard ground in order to set the support columns. At four key locations we’ll have four rebar-enforced concrete columns right next to…