Week #25 — Some doors installed, and much more

Construction crews have now built all of the columns for the final ceiling / flat roof. Once the columns are up then the workers start to connect beams from column to column. From there they place bamboo sticks every foot or so to support a plywood base for the concrete pour (in approx. 12 days). […]

Categories
Local life News Profiles Tribute

Mugging for the camera

Each time I arrive on the building site I get a hello and a wave from at least one of the many workers. Usually from quite a few. And when I raise my camera phone I tend to get a thumbs-up reaction, as a friendly imitation of my daily thumbs-up to the workers. Today one […]

Categories
Construction News Preliminary Work

Week #24 — Half the roof is done!

An exciting week here in good old Pererenan. We’ve been fortunate to stay ahead of the rainy season and cover half of the building with a roof. The other half is about two weeks away. In the meantime we have a crew for building brick walls and then plastering them. When needed the mechanical, electrical […]

Categories
Construction News Preliminary Work

Week #23 — More brick walls, plaster, and form work

There are now a total of four teams that are working daily on the project: Construction crew MEP crew (mechanical, electrical & plumbing) Brick & plaster crew Windows and doors I am not even certain of the number of people altogether, since I haven’t visited the window and door manufacturer (as usual in Bali the […]

Categories
Construction News Preliminary Work

Week #22 — Staircases, finishing concrete, and more

The structure is changing rapidly now and it’s exciting to see the development on a daily basis. There were months when the progress was like this: holes dug in the ground, mud, then more holes, more mud; concrete and steel going into the holes, then more concrete and steel (don’t forget the mud); and finally […]