Tag Indonesia

Week #13

Not every week is dramatic visually. Sometimes the preparations seemingly slow down construction, but in reality the project still moves along in a timely manner. This week the framing of the first floor (above the basement) of the residential side…

Week #12

Well folks this week we went vertical, including the famed bamboo support posts that temporarily maintain the weight of freshly poured beams and concrete floors until they harden: Does it feel good? Oh yeah, it’s like totally awesome dude 🙂

Week #11

Compacting soil, a concrete pour, then a layer of wire mesh, and finally more concrete. This defines a basement slab for the ground level. After the structure is complete a final layer creates the finish layer, such as tile or…